The City of Burnaby is moving forward with the Burnaby District Energy Utility (BDEU) project, which aims to provide the city with safe, reliable, sustainable, and cost-competitive thermal energy. The project aligns with various city policies and plans, including the Burnaby District Energy Policy (2023) and the Climate Action Framework (2020).
Project Update- The city has adopted the Integrated Project Delivery (IPD) approach for the BDEU project.
- The next phase is the Pre-Validation Phase, which will lay the groundwork for the project's success.
- The project's greenhouse gas emissions reduction will grow and align with the city's sustainability strategy.
- Validation Stage:
- Confirm project alignment
- Complete IPD team selection and onboarding
- Establish Conditions of Satisfaction & Validation
- Design and plan the initial build-out
- Develop the execution strategy
- Update the customer connection schedule
- Evaluate new building loads and investigate providing service to existing buildings
- Create the IPD Framework and Validation Plan
- Validate the business case and finalize agreements with Metro Vancouver
- Prepare an application for a BC Utilities Commission exemption
- Finalize the Validation Report
- $25.5 million of the total estimated capital costs have been included in the 2024-2028 Financial Plan.
- The IPD team will continue developing a comprehensive financial model for the Burnaby District Energy Utility.