Richmond Capital Projects Update Q3 2023

Finance Committee Minutes
Date: 2024-01-08
finance



The City of Richmond has provided a financial update on its active capital projects as of September 30, 2023. The report highlights the city's progress on various infrastructure, building, parks, land, and vehicle and equipment programs.

Capital Program Financials
  • The approved budget for all active capital projects, excluding contingent external contribution projects, was $847.7 million, of which $377.7 million or 44.6% was spent as of September 30, 2023.
  • The report provides a breakdown of the capital expenditures across different programs, including roads, flood protection, water, sanitary sewer, buildings, parks, land, and vehicle and equipment.
Key Active Capital Projects
  • Infrastructure Program:
    • Roads: $11.5 million spent, including $6.7 million on the Annual Asphalt Re-paving program.
    • Flood Protection: $8.7 million spent, including $2.5 million on Burkeville Utility Improvement projects.
    • Water: $4.9 million spent, including $3.1 million on Watermain Replacement Upgrades.
    • Sanitary Sewer: $2.8 million spent.
  • Building Program: $15.4 million spent, including $4.7 million on Richmond Ice Centre Renewals.
  • Parks Program: $6.3 million spent, including $2.0 million on Minoru Lakes Renewal projects.
  • Land Program: $12.5 million spent on potential land acquisition.
  • Vehicle and Equipment Program: $2.5 million spent, including $2.0 million on Vehicle and Equipment Reserve Purchases.