Financial Management Committee Report Reveals Progress and Delays in Major Engineering Projects
City Council Meeting
Date: 2024-02-26
transportationinfrastructure
Summary of Financial Management Committee Report on Major Engineering Projects Status Update
- Marine Drive project: Design phase complete, construction to start in Q3 2024, on schedule.
- Sidewalk Expansion Program at Alpha Secondary School: Awaiting Archaeology Impact Assessment permit, project tender under review.
- Sidewalk Expansion Program at 6th Street: Construction delayed until Provincial Heritage permits received.
- Burnaby Lake Pedestrian Bridge Overpass: Preliminary construction started, expected completion in Q4 2025.
- SFU Alternate Access Route: Design and construct emergency route connecting SFU and Mintara Restaurant parking lot, considering limited ground disturbance.